07-19-2018, 08:19 PM
I have received this update for the PG&E Streetlight upgrade work being completed.
3 week lookahead schedule is as follows:
Week of 7/16, we will be starting at the SWCO Urbano/Victoria IFO 744 Urbano, and making our way west down Urbano twds 700 Urbano, and will most likely start on De Soto once we finish on Urbano
Week of 7/23 will work on De Soto, then move to Corona St pending progress, restoring the sidewalks on Victoria next week and then up and around Urbano.
Week of 7/30 finish up De Soto/Corona If we are able to keep to this schedule, we will be done North of Holloway by 8/6
Regards,
Mark
3 week lookahead schedule is as follows:
Week of 7/16, we will be starting at the SWCO Urbano/Victoria IFO 744 Urbano, and making our way west down Urbano twds 700 Urbano, and will most likely start on De Soto once we finish on Urbano
Week of 7/23 will work on De Soto, then move to Corona St pending progress, restoring the sidewalks on Victoria next week and then up and around Urbano.
Week of 7/30 finish up De Soto/Corona If we are able to keep to this schedule, we will be done North of Holloway by 8/6
Regards,
Mark